Casablanca – Construction of the new Hassan II Stadium in Fez is approaching a major milestone, with structural work expected to finish by the end of November and the project’s first phase scheduled for completion in March 2027.
Mehdi Rahmaoui, project director at construction company TGCC, confirmed the timeline during a site visit organized for local and national media representatives on Thursday.
Speaking to Morocco’s official news agency (MAP), Rahmaoui explained that the first phase includes technical installations and roofing over the stadium’s western section, in addition to the main construction work.
“The structural work should be completed by the end of this month, while the entire first phase, including technical installations and roofing over the western section of the stadium, is expected to be completed by the end of next March,” he said.
Rahmaoui maintained that construction is progressing according to the established schedule, with work continuing simultaneously across different sections of the facility.
Up to 700 workers mobilized
Between 650 and 700 workers are currently involved in the project, covering several construction and technical specialties.
Work is progressing on the stadium’s main structures and underground facilities, with teams coordinating their activities to complete different components within the planned timeframe.
The new stadium will have a seating capacity of 15,000 spectators, replacing the former venue that was demolished to make way for the redevelopment.
Construction began in June 2026, after demolition and earthworks had been completed.
The project is divided into two phases, with the first focusing on the stadium’s structural components, technical equipment, and western roof.
A second phase will cover the building’s complete exterior cladding and architectural finishing work.
Rahmaoui did not provide a completion date for this second stage.
The March 2027 deadline therefore concerns the completion of the first phase rather than the entire stadium, which will still require additional work.
Thursday’s media visit offered journalists an opportunity to examine progress at the construction site and learn about the remaining stages of the project.
With the main structural work nearing completion, attention will now turn to the technical installations and roofing scheduled for the coming months.