Rabat – Spain has announced the start of a €5 million project to expand maritime barriers at two border points separating Ceuta from Morocco, with construction expected to take three months.
Spanish Minister of Territorial Policy and Democratic Memory Ángel Víctor Torres announced the launch of emergency works at the Tarajal and Benzú breakwaters during an appearance before the Congress of Deputies on Wednesday.
The project will extend the existing structures from 50 to 150 meters and reinforce maritime barriers along the coast. It will also include a floating containment system extending more than 500 meters, according to Torres.
The minister said the intervention carries a budget of €5 million and is expected to take three months to complete.
The project involves installing micropiles into the seabed to support the extended structures. The barriers will also include reinforced concrete elements and anti-climbing metal fencing designed to withstand maritime conditions.
A specialized vessel carrying equipment for the underwater drilling arrived at Ceuta’s port on Wednesday afternoon, according to local outlet Ceuta Actualidad. Its arrival followed an initial delay from Tuesday, when authorities had expected the vessel to reach the Spanish enclave.
The works form part of Spain’s efforts to reinforce maritime border infrastructure following the mass arrivals in Ceuta on July 30 and 31.
However, Torres said the administrative procedures for the project had started before those events. Spanish authorities had been working on securing the necessary permits, including authorization to occupy maritime public land and environmental approvals, during August, September, and October.
The expansion also follows Spain’s installation of a temporary floating barrier at the Tarajal breakwater in August. The Interior Ministry said at the time that the measure aimed to reinforce the maritime border after a Spanish Supreme Court ruling concerning the return of people who enter Ceuta or Melilla by swimming.
The project’s reported €5 million budget differs from an earlier estimate published by El País in September, which put the cost at €9 million. That estimate included €7 million for extending the breakwater and another €2 million for a permanent maritime marking and containment system.